Municipal Mismanagement or Malfeasance in Tucson?

November 12, 2025

When cities mishandle public projects, Arizonans are the ones left holding the bill. Tucson’s Downtown Links project—sold to voters in 2006 as a straightforward $76 million improvement—has instead become a sprawling, over-budget undertaking that illustrates exactly why independent watchdog oversight is essential in Arizona. For years, the Goldwater Institute, where I work, has warned that without firm guardrails, local governments can quietly shift the costs of their own mismanagement onto taxpayers who never agreed to foot the bill.

That pattern has played out repeatedly over the life of the project. The Downtown Links project shows in concrete terms how mismanagement at the local level can inflate costs, distort voter-approved plans, and leave regional taxpayers paying for decisions they didn’t make. The City of Tucson has managed to burn through a significant amount of taxpayer money on a project covering just 1.3 miles—from Broadway to St. Mary’s. Although the project is funded through the 2006 voter-approved Regional Transportation Authority (RTA) plan, it is Tucson—not the RTA—that is responsible for planning, managing, and executing the work.

On Wednesday, October 29, 2025, the City of Tucson submitted its eighth request for additional funds. Voters were told in 2006 that the project would cost $76 million. The city’s own Intergovernmental Agreement (IGA) with the RTA also requires Tucson to cover any amounts exceeding the 10 percent overrun permitted under state law and RTA policy. Yet the city returned once again for help, and the RTA board approved the latest request, pushing total costs past $110 million for a project voters expected to be finished by 2021, the end of the third five-year period in the original 20-year plan.

Each amended request varied in excuses for the additional costs, with some more credible than others. Additional amounts were spent on drainage, some was spent on right-of-way acquisition, utility relocation, along with several other unexpected costs. What remains unclear is why the city continues returning to the RTA for funds that require taxpayers across Pima County to absorb overruns Tucson agreed to cover itself.

The city has repeatedly acknowledged that it—not regional taxpayers—is responsible for any cost overruns beyond the 10 percent allowance. A memo to the mayor and city council on April 8, 2025, reaffirmed that obligation. Other jurisdictions managing RTA projects have absorbed their overruns without shifting the burden onto the rest of the county. So why is Tucson consistently treated differently, with the RTA covering costs the city agreed to shoulder?

The latest explanation offered to the RTA board by city officials is that telecom utility relocation near the railroad tracks, combined with prolonged difficulties coordinating with Union Pacific on the tunnel design, caused multiple delays and increased costs. The project is now targeted for completion sometime in 2026, five years after the voters were told the job would be finished.

This project is already $34 million over budget and counting. How many more times will Tucson ask the RTA board to cover additional costs? And at what point do taxpayers across Pima County get a meaningful opportunity to say no to more bailouts for a project that has long since blown past its voter-approved limits?

At some point, bad luck starts to look like mismanagement—or worse. The patience of Pima taxpayers has begun to wear thin.

William Beard is the Municipal Affairs Liaison at the Goldwater Institute.

 

 

More on this issue

Donate Now

Help all Americans live freer, happier lives. Join the Goldwater Institute as we defend and strengthen freedom in all 50 states.

Donate Now

Since 1988, the Goldwater Institute has been in the liberty business — defending and promoting freedom, and achieving more than 400 victories in all 50 states. Donate today to help support our mission.

We Protect Your Rights

Our attorneys defend individual rights and protect those who cannot protect themselves.

Need Help? Submit a case.

Get Connected to Goldwater

Sign up for the latest news, event updates, and more.

Wait! Don’t close this yet!

We are grateful for your support of the Goldwater Institute’s efforts to advance and defend liberty throughout the United States. For over 36 years, we’ve been defending the rights of Americans to live their lives free from government interference.

And Goldwater is unique in that we direct our efforts to the 50 states where we introduce and advance innovative ideas that expand freedom. And we fight in courtrooms and capitals nationwide to defend individual liberty.

In 2024 alone, we scored over 50 policy and litigation victories defending liberty!

And that’s just the beginning.

Our plans for 2025 include:

  • Stopping pernicious DEI and other woke programs in America’s universities.
  • Ensuring that patients suffering from rare and terminal diseases have access to cutting-edge, lifesaving medical treatments, without having to first seek permission from the government.
  • Defending parental rights across the United States so that parents can send their kids to the school that best fits their needs, free from leftist indoctrination.
  • Eliminating government interference in the fundamental right of individuals to own property and use it as they see fit.
  • And much, much more

We seek to restore the presumption of liberty; that people are free to act without first asking permission from the government.

But we cannot do this without you. Will you join us as we fight to preserve and advance liberty throughout the country? As we seek new and innovative ways to defend freedom in all 50 states?

And there’s great news: Thanks to a generous Goldwater supporter, your donation today will be doubled!

So please, join us in fighting to advance liberty and score real wins for freedom from coast to coast!